Data release [made at SA Director of Mines' discretion] : Eucla Basin Project tenement Group 1. Joint annual reports, for the period 1/1/2016 to 31/12/2018. Plus EL 6369 surrender.
27 contiguous licence areas within the eastern Eucla Basin, that span a combined 21,772 square km of ground between points as far as 90 km north of the Trans Australian Railway, 50 km east of Nullarbor and extending right down to the coastline, and...-
Document
Published: 28 Feb 1919
-
Barton, Barton Range North and Paling Range, plus Wells and north-eastern Eucla Basin licence Areas A through Y (Iluka's Eucla Basin Heavy Mineral Sands Project tenement Group 4). Joint annual reports for the period 19/10/2009 to 31/12/2015.
During the 2009-2010 project reporting year, Iluka completed exploration work costing $5,200,532 across its combined thirty-one Group 4 tenements, to assess the north-eastern Eucla Basin's sediment stratigraphy and heavy mineral sand (HM) potential...-
Document
-
The Mindarie Heavy Mineral Sands Project. Joint and combined annual reports, for the period 19/12/1997 to 31/12/2010.
An assessment of the Late Tertiary Murray Basin shallow marine clastic sedimentary sequence (Loxton and Parilla sands) for heavy mineral sand accumulations has discovered numerous occurrences of economic to sub-economic amounts of heavy minerals...-
Document
Published: 19 Apr 1911
-
Data release - as updated [made at SA Director of Mines' discretion] : Murray Basin Project. Joint annual reports, plus individual licence final reports at their respective full surrender, for the period 19/12/1997 to 30/6/2018.
Previous investigations of the Late Tertiary Murray Basin shallow marine littoral zone clastic sedimentary sequence (Loxton and Parilla sands) for heavy mineral sand (HM) placer accumulations have discovered numerous occurrences of economic to...-
Document
-
The Adelaide Hills Project (now including the former Fleurieu Project tenements). Annual reports for the period 1/10/2013 to 30/11/2018 plus expiry/full surrender reports to 7/10/2023.
During the twelfth, 2013-2014 project year, work on the now combined licence holdings of the Terramin Group focussed on prospect evaluation done at Bird-in-Hand (environmental and hydrological studies), Wheal Barton and Golden Slope, plus the ongoing...-
Document
-
Meribah, Halidon, Mantung, Karoonda and Woolpunda (parts of the Murray Basin HMS Project). Individual licence first or second partial surrender reports, describing relevant subsets of exploration work performed between 29/9/1997 and 5/9/2018.
Portions of the Tertiary shallow marine clastic sedimentary sequence (Loxton and Parilla sands) deposited in the central western Murray Basin within SA's Murray Mallee district have been explored for possible economic heavy mineral sand (HMS)...-
Document
-
Ilkina, Acraman, Yarranna Hill, Poondana Rock, Waddikee Rocks, Mount Sturt, Yaninee, Nunjikompita, Poochera, Wandana and Smoky Bay (Narlaby Palaeochannel area). Combined progress and technical reports for the period 5/1/81 to 31/12/83.
Carpentaria's exploration for sandstone type uranium deposits in the West Coast region of SA over the period 1979-1982 has revealed a major Tertiary buried palaeochannel system. The main Narlaby Palaeochannel is 170 km long, up to 10 km wide and is...-
Document
-
Midgerie, Barton South, Immarna, Barton Siding, Mount Christie Siding, Lake Bring, Mulgathing, Wynbring (TARCOOLA and BARTON 1:250k mapsheets region). Joint progress reports and final reports, for the period 11/4/1981 to October 1990.
Stockdale's exploration for diamonds in the Barton region, at the start of the licence period, commenced with the evaluation of 136 potential kimberlite targets generated by the detailed in-house interpretation of data acquired from an extensive new...-
Document
-
Mount Miccollo, Tin Hut Hill, Eurilla Dam, Wilcherry Hill, Uno, Peterlumbo and Mount Double (the Wilcherry Hill Project). Joint annual reports for the period 1/11/2002 to 31/10/2018.
During Year 6 of the project, Trafford Resources designed their drilling program to test the extent of the Pb/Zn/Ag/U mineralisation at the Telephone Dam Prospect, while JV partners Ironclad Mining’s drilling program was designed to define the Direct...-
Document
-
The Murray Basin Project. Joint progress reports and joint final report to remnant licences' full surrender, for the period 7/10/1980 to 6/12/1984.
Thirteen contiguous exploration licences located along the western margin of the Tertiary Murray Basin were taken up by CRA to search for economic buried brown coal / lignite deposits of the type already known from small discoveries that had been made...-
Document
Published: 07 Mar 1985
-
The Padthaway Ridge Sedimentary Uranium Project. Joint annual technical reports to licences' combined full surrender, for the period 30/1/2008 to 3/9/2013.
A package of fourteen mineral exploration tenements were taken up that straddled the north-eastern and south-western sides of the Padthaway Ridge, to allow the licensee to explore both the Tertiary Murray Basin and Gambier Basin sediments where they...-
Document
Published: 16 Jul 1913
-
The Musgrave Project. Joint annual reports for the period 5/10/2007 to 31/1/2012 [as later updated, to include additional licences, to 31/1/2017], plus respective successive full surrender final reports for individual licences.
The multi-licence Mithril - Barrick JV Musgrave Project area is centred 600 km south-west of Alice Springs, within the APY Lands of north-western South Australia. It is considered to be prospective for buried economic Ni-Cu-PGE sulphide mineral...-
Document
Published: 09 Oct 1917
-
Poondinga, Jellabinna, Pureba North, Kalanbi, Penong, Chinta and Ceduna (the Eucla Basin Heavy Mineral Sands Project tenement Group 2). Joint annual reports for the period 2/11/2004 to 30/9/2015.
Iluka Resources’ Eucla Basin Heavy Mineral Sands Project tenement Group 2 consisted initially ELs 3268, 3283, 3322 and 3330, which spanned the south-eastern portion of the Eucla Basin, extending from 24 km to 140 km north of Ceduna. Regionally, the...-
Document
Published: 28 Feb 1916
-
Data release - as updated [made at SA Director of Mines’ discretion] : (for 10 exploration licences comprising) the Lake Torrens JV Project. Joint annual reports for the period 1/1/2007 to 31/12/2011.
A group of ten, mainly adjoining licence areas occupying the plains surrounding the northern end of Lake Torrens, are now being jointly explored for possible economic buried Olympic Dam style IOCG related mineralisation that may have formed in the...-
Document
-
The MIM-Peko Stuart Shelf Joint Venture Project. Progress reports to licences' joint full surrender and their re-issue as a single replacement tenement, for the period 15/2/1983 to 20/10/1989.
Exploration for Olympic Dam-style Cu-Au-U mineralisation, undertaken over areas to the south-east of Arcoona Homestead and in the vicinity of Woomera township, has comprised numerous reconnaissance and then detailed gravity, ground magnetic and CSAMT...-
Document
-
Chimpering Rock Hole, Yarrana Hill, Moornaba Rock Hole, Euria Well, Koonibba Mission, Lake Tallacootra, Dunn Hill, Wallala Hill, Mount Centre and Nalara. Quarterly and annual progress reports plus technical reports, for the period 25/7/1989 to 24/7/1992.
Hitherto untried exploration for heavy mineral sands on the eastern margin of the Eucla Basin, conducted by the Ceduna Joint Venture partners since 1989 over ten contiguous licence areas in the Ooldea - Barton area centred 150 km north-west of Ceduna,...-
Document
-
Data release [made at SA Director of Mines' discretion] : Painted Hill, Birthday Hill, White Hill, Mount Hawker and The Twins (the Mount Woods Project). Progress and combined annual reports for the period 27/11/1987 to 31/12/2007. [ Index Part 4 of 4 ].
In 2006, work completed on the Prominent Hill Project in the reporting period included drilling of 17 RC holes for 4,255 m and 46 mud/diamond holes at Prominent Hill prospect for 14,301.5 m. The drilling at Prominent Hill intersected wide zones of...-
Document
-
Eucla Basin Areas E, J, L, M, N, O and Z: part of Iluka's Eucla Basin tenement Group 4. Final joint annual report at licences' joint full surrender, for the period 19/10/2009 to 7/4/2016.
Seven exploration licences which together comprised the western portion of Iluka's Group 4 of jointly reported tenements have been fully surrendered, after work performed there recently suggested that their perceived prospectivity for Tertiary...-
Document
Published: 18 Dec 1916
-
Bopeechee and Cadnia Hill/Stuart Creek and Porter Hill (The Lake Torrens Project). Data release made at two licences' surrender/two latter licences' fifth partial relinquishment: annual reports and final reports for the period 9/4/1998 to 31/12/2006.
The reports comprising this data release package describe exploration for economic deposits of base and precious metals that have possibly formed within Neoproterozoic metasediments, the underlying Palaeoproterozoic basement, and in Cambrian carbonate...-
Document
Published: 29 Sep 1909
-
Burra Project licence group. Data release made in lieu of submitting partial surrender reports for ELs 6102, 6103, 6158, 6305 and 6306 : joint annual reports for the period 25/1/2018 to 2/12/2020 plus initial annual annual report.
To date exploration in the Burra region of the Adelaide Geosyncline has focussed on historic copper-gold oxide workings, with the aim of delineating further mineralisation along strike, or sulphide mineralisation at depth. Lately however, rather than...-
Document
Published: 04 Feb 1921