Feasibility level geotechnical and hydrogeological studies, Moorlands coal deposit, Lobe E, Moorlands SA.
Drilling (132.8 metres) included fully cored geotechnical hole to basement to estimate mine planning constraints for open cut mining. The unconfined aquifer above the lignite must be dewatered for mine slope stability. Overburden contains 2 layers of...-
Document
-
Moorlands. Progress reports and final report to licence full surrender, for the period 15/1/1979 to 30/11/1984.
Adelaide Brighton Cement took up tenure of the Moorlands lignite deposit during September 1976 in order to conduct confirmatory drilling of the published coal resource, to prepare a mining study for Lobe 'E', and overall, to assess the coal's...-
Document
Published: 23 Nov 1984