RB 60/00111 River Murray drainage investigation. Progress report no. 2 - stratigraphy and micropalaeontology of bores and surface sections.
Stratigraphic data are provided for: Waikerie Pumping Station - cliff section, Waikerie Bore No. 1, Waikerie Bore No. 1A, Ramco Heights Bore No. 1, Sunlands Pumping Station - cliff section, Sunlands Bore No. 2 and Tolleys Rising Main section (all in...-
Document
Published: 02 Jun 1965
-
RB 89/00049 Aspects of stratigraphy and structure in relation to the Woolpunda Groundwater Interception Scheme, Murray Basin, South Australia.
Micropalaeontological and biostratigraphic studies have been used. Groundwater flow systems were investigated near the Woolpunda Groundwater Interception Scheme (WGIS) - a major area of saline groundwater discharge to the Murray River. Structure was...-
Document
Published: 01 May 1989
-
Cronje Dam and Oak Bank Outstation (the Cronje Dam Sedimentary Uranium Project). Annual and joint annual reports, plus final report at remaining licence's expiry/full surrender, for the period 20/10/2005 to 1/11/2014.
An area comprised of three separate sub-blocks generally located ~60 km south of Manna Hill and ~70 km south-southeast of Olary has been explored for Tertiary sedimentary uranium which may have formed in buried north to south trending palaeochannels...-
Document
-
RB 63/00062 River Murray drainage investigation progress report no. 7, stratigraphy and micropalaeontology of bores, Hds Waikerie and Pyap.
Stratigraphic summaries and more significant microfaunal data are provided for additional water bores on properties in the Sunlands, Ramco and Waikerie areas, and for a recently completed bore at New Residence, 7 miles south of Moorook. Formations of...-
Document
Published: 01 Jan 1966
-
RB 2000/00037 Qualco Sunlands groundwater control scheme - Stage 2: QS9 drilling and well testing completion report.
The contract drilling of three production wells, three combined interflow/production wells, three interflow wells, one observation well and seven drainage wells was carried out by Thompson Drilling Company as part of Stage 2 of the Qualco Sunlands...-
Document
Published: 01 Sep 2000