Continuous solvent extraction studies.
Work carried out at Amdel and at the Colorado School of Mines' Research Institute has indicated that both a two solvent system (EHPA and TBP or DBBP) and a three solvent system (EHPA, DBBP and Alamine 336) of cationic exchangers are satisfactory for...-
Document
-
RB 37/00078 Preliminary investigations into corrosion of stainless steels during leaching of uranium concentrates from Radium Hill, South Australia.
Corrosion tests were carried out on several types of stainless steel to determine their suitability for use in the construction of components for digesters to be used for the leaching of Radium Hill ore concentrates. The testing was carried out under...-
Document
Published: 12 Apr 1954
-
RB 37/00134 Report on the absolute age of the uraniferous granite and Precambrian tillite in the Crocker Well area, Olary district, South Australia.
There is no abstract created for this record-
Document
Published: 01 Jan 1954
-
RB 40/00001 Report on investigation of uranium deposits at Mount Painter, South Australia, (during the period) June 1944 to September 1945.
Part titles for RB 40/00001: Part I. General statement - Investigation of uranium deposits, Mount Painter, South Australia. Part II. Construction and mining operations. Part III (1). Uranium minerals from Mount Painter. Part III (2). Reconnaissance...-
Document
Published: 08 Nov 1945
-
RB 41/00059 Thickening and filtration of Radium Hill tailings products (RD 28).
Plant tests conducted at Radium Hill on the effect of reagent S3000 on the settling and thickening characteristics of the tailings products are described.-
Document
Published: 01 Jan 1955
-
SADM/Amdel Project MP 1/1/172: In situ leaching of uranium (Honeymoon deposit, Frome Embayment). [Results of analytical, mineralogical and metallurgical testwork performed on diamond drill core samples]. Progress reports 1-6, May 1975 to November 1976.
At the request of Mines Administration and of the South Australian Mines Department, Amdel has undertaken a project designed to obtain data on the in situ leaching potential of the uranium ore in the Honeymoon deposit, located in the Lake Frome region...-
Document
Published: 05 Nov 1976
-
Data release - as updated [made at SA Director of Mines' discretion] : Wild Horse Plain. Annual reports for the period 8/7/2005 to 23/2/2019, plus partial surrender reports to 23/2/2021.
An upland area located approximately 100 km south-west of Whyalla on the eastern Eyre Peninsula, and with its eastern boundary running parallel to the coast at a distance of 15 km from Cowell and Franklin Harbour, is being explored for uranium,...-
Document
Published: 11 Jan 1921
-
Mount Miccollo, Tin Hut Hill, Eurilla Dam, Wilcherry Hill, Uno, Peterlumbo and Mount Double (the Wilcherry Hill Project). Joint annual reports for the period 1/11/2002 to 31/10/2018.
During Year 6 of the project, Trafford Resources designed their drilling program to test the extent of the Pb/Zn/Ag/U mineralisation at the Telephone Dam Prospect, while JV partners Ironclad Mining’s drilling program was designed to define the Direct...-
Document
-
Data release - as updated [made at SA Director of Mines’ discretion] : Tarcoola. Annual reports for the period 2/6/2008 to 29/7/2018.
During the first year of renewed EL 4167, in October and November 2008, Stellar Resources Ltd ("Stellar") completed a 5 hole, 1286.9 m RC and 2 hole, 157.1 m diamond cored inclined drilling programme at the Coolybring prospect which is located...-
Document
Published: 11 Sep 1918
-
Data release - as updated [made at SA Director of Mines' discretion] : Mutooroo (the Olary Creek Project). Annual reports for the period 15/11/2005 to 7/2/2019.
An area centred ~50 km south west of Cockburn is being explored for possible economic base and precious metal mineralisation that may have formed in buried Palaeoproterozoic basement rocks, as well as for any secondary uranium mineralisation that may...-
Document
-
Data release - as updated [made at SA Director of Mines’ discretion] : Arkaroola. Annual reports for the period 5/12/2008 to 3/12/2015.
During the 2008-2009 licence year, most of the new work done consisted of appraisal rotary mud drilling at Four Mile East (112 holes for 24,460 m) and Four Mile West (113 holes for 19,120 m), with the addition of one NQ diamond cored hole (AKC093) for...-
Document
Published: 20 Jan 1916
-
Lake Frome [part of the Paralana Plains Uranium Project joint venture area]. Progress reports and technical reports to licence surrender/re-issue over a different area, for the period 22/4/1971 to 21/4/1973.
Exploration on SML 564 has consisted of a continuation of deep rotary mud open hole, plug and core drilling plus washing-out of existing, older Petromin "P...w" series drillholes to allow new generation downhole geophysical logging, aimed at further...-
Document
-
Honeymoon "in situ" leach tests.
The major aim of this project is to develop a method of leaching a range of ore types in the Honeymoon deposit using the push-pull technique. For alkaline leaching, reagent conditions were based on laboratory bottle roll studies and data from the...-
Document
-
Paralana Creek and Four Mile Creek [part of the Paralana Plains Joint Venture area]. Progress reports for the period 15/4/1968 to 14/4/1971.
A licence area covering the flat alluvial Paralana Plains extending out eastwards from the northern Flinders Ranges was taken up by the the consortium of Exoil NL, Petromin NL and Transoil NL to explore for possible economic buried occurrences of...-
Document
-
Preliminary [mining] feasibility study [for the] Lake Frome uranium orebodies. Final report.
Report presents the results of a preliminary study of the commercial feasibility of producing yellowcake from the Beverley sedimentary uranium deposit located near Lake Frome. All of the available drillhole data for this deposit was examined and...-
Document
-
Data release [made at SA Director of Mines’ discretion] : Gum Flat. Annual reports submitted prior to the commencement of joint reporting on the Gum Flat Iron Ore Project, for the period 27/9/2005 to 26/9/2008.
An area lying immediately west of Port Lincoln and extending for ~10 km inland is being explored for buried occurrences of multiple metallic mineral commodities that may have been deposited within faulted, folded and metamorphosed Archaean basement...-
Document
Published: 20 Nov 1907
-
Comet Outstation, Gina Outstation, Commonwealth Hill Station - Central and East, and Aurora Tank areas (the Commonwealth Hill Project). Joint annual reports for the period 15/12/2008 to 30/6/2013.
A group of contiguous exploration licences centred ~100 km south-west of Coober Pedy are being explored principally for epithermal and Challenger-style gold mineralisation hosted by covered Archaean basement rocks, as well as for any economic base...-
Document
Published: 31 Aug 1913
-
Mount Kingston. Progress reports and final report to licence expiry/full surrender, for the period 10/10/1979 to 26/4/1984.
Diamond exploration undertaken over an area situated 70 km south-east of Oodnadatta included photogeological studies, the acquisition of a 2400 line km low level aerial magnetic and radiometric survey, and geochemical analyses of 452 reconnaissance...-
Document
-
Data release [made at SA Director of Mines' discretion] : Moonta - Wallaroo area (where licence is subject in part to the Moonta Porphyry Joint Venture). Annual reports for the period 24/12/1996 to 11/4/2008. [ Index Part 1 of 2 ].
A 106 square km area, comprising two blocks which cover the main historic copper and gold - producing districts centred around the towns of Moonta and Kadina, is being explored afresh in an attempt to identify ore resources of quantity sufficient to...-
Document
-
Crocker Well ore [beneficiation] (Appendix 6 in quarterly report to 23/9/1977).
Past beneficiation studies on the unusual Crocker Well absite - brannerite ore assemblage have been researched for the benefit of Esso Minerals. It appears that the Crocker Well ore responded favourably to flotation. Concentration ratios in the...-
Document
Published: 03 Nov 1976