-
Summary report on Honeymoon assessment programme (Phase 1), Honeymoon uranium deposit, South Australia.
This report summarises results of a rotary drilling and coring programme undertaken between 21/10/1978 and 16/2/1979 at the Honeymoon uranium deposit. 99 open plug holes totalling 12,452.7 m and 16 core holes totalling 1894 m were drilled in a...-
Document
-
Yarramba. Progress reports to licence expiry/renewal for the period 8/3/1976 to 7/3/1978.
Ongoing exploration for sedimentary uranium ore deposited in buried 1.5 - 6 km wide and 50 m thick Tertiary palaeochannels in the Yarramba area, located adjacent to the SA-NSW border 50 km northwest of Cockburn, included three detailed and...-
Document
Published: 17 Apr 1978
-
South Eagle. Progress and technical reports for the period 21/12/1977 to 2/11/1984.
TARGET: Ongoing evaluation of the Honeymoon deposit. EXPLORATION: Pilot wellfield drilling (48 holes) on a 60 m by 30 m grid over the eastern half of the deposit, hydrological investigations, metallurgical testing, and in-situ push-pull leaching...-
Document
Published: 10 Nov 1984
-
Lake Elder, Lakeside and Thurlooka Bore (Lake Elder Project). Annual, progress and final reports to licences' expiry/full surrender for the period 21/8/1997 to 20/8/2001.
A review of existing drillhole information from the area between Lake Frome and the NSW border targeted sedimentary uranium in Tertiary palaeochannels. 15 rotary holes totalling 1873 m were drilled in two interpreted palaeochannels, but returned no...-
Document
-
Starvation Lake. Final report to licence surrender for the period 22/5/1972 to 21/5/1973.
As part of an ongoing search for possible buried economic roll-front or sandstone type Tertiary sedimentary uranium deposits in an area 70 km east of Lake Frome, a detailed stratigraphic and sedimentological analysis was undertaken of rotary drillhole...-
Document