PACE Theme 2 (drilling partnerships with PIRSA and industry): Year 3 partnership DPY3-04, Churchill Dam area iron oxide - associated copper-gold and uranium mineral prospect. Project interim and final reports.
EL 3511 licensee Debnal and its joint venture partner Venture Minerals are exploring an area of the eastern Gawler Craton having a predicted high potential for the discovery of Olympic Dam type iron oxide - associated copper-gold-uranium (IOCG-U)...-
Document
-
Data release [made at SA Director of Mines' discretion] : Yeltacowie (part of the Mount Gunson Project). Annual reports for the period 30/7/2003 to 6/10/2009.
The subject EL 3112 ground represents the continuation of tenure by Gunson Resources, over the same area, from its former EL 2516 Yeltacowie (for which see the relevant licence reports previously released in Envs 9530 and 9715). This replacement...-
Document
-
Tarcoola - Tallaringa Bedrock Drilling Project.
Archaean, Early and Middle Proterozoic rocks of the north-western Gawler Craton have features which suggest good prospectivity for base metals, precious metals and other commodities. However, outcrop is poor and there has been relatively little...-
Document
-
Data release - as updated [made at SA Director of Mines’ discretion] : Oak Dam North-east. Annual reports for the period 18/1/2006 to 17/1/2011.
A relatively large but little-explored area of the central-eastern Stuart Shelf, which is almost wholly covered by scrubby sand dunes and swampy salt lakes, thereby making surface access very difficult despite it being located only ~30 km to 50 km km...-
Document
Published: 16 Mar 1911
-
Data release [made at SA Director of Mines' discretion] : Acropolis South and North Roxby. Joint annual reports for the period 26/4/2003 to 3/5/2009.
Exploration for possible economic deposits of buried, Mesoproterozoic basement-hosted IOCG-U style mineralisation is being conducted over two separate multiple-block licence areas in the Olympic Dam district, EL 2931 (Acropolis South) and EL 2932...-
Document
-
Data release - as updated [made at SA Director of Mines' discretion] : Mount Gunson (part of the Mount Gunson Project). Annual reports for the period 18/10/2008 to 24/3/2018.
During licence Year 15 (2008-2009), activities at Mount Gunson comprised: - pegging of three Mineral Claims at the MG 14 deposit in December 2008; - acquiring part of a larger project-wide ground gravity survey during April-May 2009 (510 stations...-
Document
Published: 22 Aug 1918
-
Data release - as updated [made at SA Director of Mines' discretion] : Yeltacowie (part of the Mount Gunson Project). Annual reports for the period 7/10/2009 to 6/10/2013.
New work undertaken on EL 4187 during the 2009-2010 licence year has included: • Ongoing documentation and interpretation of MGD 55 & 56 • Drilling of MGD57 to 1243 m at Emmie Bluff prospect • Down hole EM and IP logging of MGD57 •...-
Document
-
Data release - as updated [made at SA Director of Mines' discretion] : Eucolo Creek (also called the Churchill Dam Project). Annual reports for the period 31/1/2006 to 14/11/2018.
EL 3511 Eucolo Creek, of 528 square km, is situated near the eastern margin of the Gawler Craton within the Olympic Dam Domain, approximately 90 km south-west of the Olympic Dam IOCG-U deposit (3.98 billion tonnes at 1.1% Cu, 0.4 kg/t U3O8 and 0.5 g/t...-
Document
Published: 01 Dec 1918
-
Lake Ross, Lake Hanson, Kowal and Gosses areas (Glendambo Project). Annual and final reports for the period 18/3/97 to 3/4/2000.
Interpretation of existing geophysical and drillhole data, including core chip re-assaying and petrography, was carried out for four areas located approximately 60 km north-west of Woomera. Interpreted geophysical features of the basement are...-
Document
-
Bulgunnia. Annual reports and final report to licence expiry/full surrender, for the period 10/12/1996 to 9/12/2000.
A significant combined thickness of Late Proterozoic Pandurra Formation, Jurassic Algebuckina Sandstone and Cainozoic sediments overlies prospective Middle Proterozoic basement 70 km north of Tarcoola. Several gold anomalies were returned from...-
Document
-
Sloane Hill East. Annual and final reports to licence expiry/full surrender for the period 19/4/2007 to 18/4/2009.
Exploration for possible economic IOCGU mineralisation which was carried out in an area located approximately 22 km south-east of the Prominent Hill mine has consisted of the acquisition of a detailed gravity survey that covered the entire tenement...-
Document
Published: 05 Jun 1909
-
Emmie Bluff. Progress reports to licence expiry/full surrender, for the period 3/3/1975 to 2/3/1976.
Exploration for possible economic buried Olympic Dam-style Cu-Au mineralisation, undertaken over an area located 15 km south-east of Arcoona Homestead, comprised preliminary airphoto interpretation and surface geological mapping, outcrop sample...-
Document
Published: 12 Mar 1976
-
Pernatty Lagoon. First partial surrender report at licence expiry/renewal, for the period 20/7/1973 to 19/7/1975.
Exploration conducted by CSR Ltd for possible economic stratiform base metal deposits in the western part of EL 81 addressed several targets, including Cattle Grid type disconformity - related copper mineralisation, Sweet Nell / MG14 type...-
Document