Mount Gunson - Pernatty. Quarterly reports and annual reports to licence expiry/full surrender, for the period 14/2/1987 to 15/4/1994.
Ongoing copper exploration in the Mount Gunson area was directed primarily at locating economic stratiform mineralisation in the Tapley Hill Formation, which overlies Pandurra Formation and the associated Cattlegrid orebody. New work comprised...-
Document
-
Andamooka, Stuart Creek, Arcoona, Lake Torrens, Todds Dam, Lake Arthur, Woodforde Hill and Murdie Island (the Stuart Shelf Project). Joint first partial surrender report at licences' expiry/renewal, for the period 2/5/1975 to 16/6/1986.
WMC's Stuart Shelf exploration activities from 1975 to 1985 have sought mainly Olympic Dam style mineralisation (copper - uranium - precious metals in haematitic breccia host rocks), with lesser emphasis directed at: possible distal analogues of the...-
Document
-
Jenner Hill, Pearson Hill and Sandy Point (the Stuart Shelf JV Project). Joint progress reports, plus later annual reports and final report to full surrender of remnant licence EL 1808, for the overall period 4/10/1989 to 24/10/1996.
Exploration for Olympic Dam-style mineralisation, undertaken over an area centred ~15 km south-east of Arcoona Homestead on the Stuart Shelf, which includes WMC's formerly partly tested Emmie Bluff prospect, has comprised the acquisition of ground...-
Document
-
Unlocking South Australia's Mineral and Energy Potential - A Plan for Accelerating Exploration. Theme 2 (drilling partnerships with PIRSA and industry) : Year 4 partnership no. DPY4-65, Chianti mineral prospect. Project completion dataset.
The subject set of reports describes the results of PACE Initiative Year 4 partly-subsidised drilling work conducted in the vicinity of the Chianti prospect, which lies approx. 20 km north of the old Mount Gunson mining camp. The aim of this work,...-
Document
-
Mount Gunson, Woocalla, Bernard Hill, Mount Moseley and Emmie Bluff (the Mount Gunson Project). Respective second to fourth partial surrender reports, for the overall period 15/7/1994 to 12/10/2004.
No work has been undertaken on the currently relinquished portions of ELs 3112, 2639, 3008 and 3022. However, as an attachment to the current EL 3112 relinquishment report, all technical data for Stuart Metals' recent diamond drillhole MGD24 (to...-
Document
-
Data release - as updated [made at SA Director of Mines’ discretion] : Oak Dam North-east. Annual reports for the period 18/1/2006 to 17/1/2011.
A relatively large but little-explored area of the central-eastern Stuart Shelf, which is almost wholly covered by scrubby sand dunes and swampy salt lakes, thereby making surface access very difficult despite it being located only ~30 km to 50 km km...-
Document
Published: 16 Mar 1911
-
Data release [made at SA Director of Mines' discretion] : Acropolis South and North Roxby. Joint annual reports for the period 26/4/2003 to 3/5/2009.
Exploration for possible economic deposits of buried, Mesoproterozoic basement-hosted IOCG-U style mineralisation is being conducted over two separate multiple-block licence areas in the Olympic Dam district, EL 2931 (Acropolis South) and EL 2932...-
Document
-
Data release - as updated [made at SA Director of Mines' discretion] : Carrapateena Arm, Hatch Hill, Beda Arm and Lake Torrens South (the OZ Minerals Carrapateena Project). Annual reports (separate and joint) for the period 8/1/2008 to 6/1/2016.
Exploration of the Lake Torrens JV Project area during 2008, managed by Teck Cominco Australia (Teck), consisted of diamond drilling some wedge holes off a parent to determine the lateral and vertical dimensions of bornite and chalcopyrite - dominated...-
Document
-
Data release [made at SA Director of Mines' discretion] : Mount Gunson (part of the Mount Gunson Project). Annual reports for the period 15/7/1994 to 17/10/2008 [ Index Part 4 of 4 ].
During licence Year 12, following encouraging results made by its continuing exploratory drilling, Gunson Resources was able to negotiate a joint venture over the Mount Gunson Project tenements with Falconbridge Limited through its subsidiary Noranda...-
Document
-
Data release [made at SA Director of Mines' discretion] : Mount Gunson (part of the Mount Gunson Project). Annual reports for the period 15/7/1994 to 17/10/2008 [ Index Part 3 of 4 ].
During the eighth year of tenure, work done on EL 2639 included: - the conduct of infill ground gravity and CSAMT surveys; - geophysical modelling and interpretation of the new survey data; - geological interpretation and refinement of drilling...-
Document
-
Data release [made at SA Director of Mines' discretion] : Mount Gunson (part of the Mount Gunson Project). Annual reports for the period 15/7/1998 to 17/10/2008 [ Index Part 2 of 4 ].
Stuart Metals is primarily exploring EL 1946 for stratiform copper mineralisation of the various styles known to be present in the Mount Gunson district. In addition, the company regards the largely unknown Mesoproterozoic basement to have strong...-
Document
-
Salt Creek. Progress reports to licence expiry/renewal, for the period 13/9/1976 to 12/9/1978.
Possible buried stratabound copper mineralisation of Mount Gunson / Cattlegrid type was the target of exploration performed on an area of the Stuart Shelf located 60 km east of Woomera. After conducting detailed 1:12,000 and 1:16,000 scale geological...-
Document
-
Data release - as updated [made at SA Director of Mines' discretion] : Mount Gunson (part of the Mount Gunson Project). Annual reports for the period 18/10/2008 to 24/3/2018.
During licence Year 15 (2008-2009), activities at Mount Gunson comprised: - pegging of three Mineral Claims at the MG 14 deposit in December 2008; - acquiring part of a larger project-wide ground gravity survey during April-May 2009 (510 stations...-
Document
Published: 22 Aug 1918
-
Stuart Shelf Project. EL 1338 first [and Project second overall] partial surrender report, for the period 2/5/1975 to 16/6/1991.
TARGET: Possible buried base and precious metal deposits associated with aeromagnetic anomalies, and also with either coincident or unrelated gravity anomalies, lying within a relinquished sector of the large contiguous multi-licence area that Western...-
Document
-
[Final] Summary report, SML 204, SA.
BHP took out SML 204, covering 970 square miles located due east of the northern Middleback Range, for 2 years from 1/7/1968. The prime objective was to explore there for uranium and copper mineralisation. Work undertaken can be summarised as...-
Document
-
Bull 033 The Geology and Iron Ore Resources of the Middleback Range Area
This report deals comprehensively with the physiography, prospect geology, and ore genesis, and includes an assessment of the iron ore reserves and other mineral resources of an area which has been almost the sole source of the iron ore used in...-
Document
-
Winjabbie. First partial surrender report at licence expiry/renewal, for the period 20/10/2005 to 19/10/2010.
The western half of EL 3432, which now lies within the continuously restricted access Red Zone of the Woomera Prohibited Area, has been relinquished at expiry of term, acting upon advice received from DMITRE. During its 5-year tenure period the...-
Document
Published: 03 Dec 1912
-
PACE Theme 2 (drilling partnerships with PIRSA and industry): Year 6 partnership DPY6-07 - Intercept Hill JV Project, central Stuart Shelf area - Oak Dam South Proterozoic basement IOCG mineral prospects. Drilling project final report.
The Intercept Hill Project area is located in the central part of the Stuart Shelf. Gawler Craton basement rocks in the project area comprise leucocratic granite of the Hiltaba Suite, volcanic rocks of the Gawler Range Volcanics and metasediments of...-
Document
-
Intercept Hill. Annual reports to licence expiry/full surrender, for the period 8/5/2003 to 14/7/2013. [Index Part 1 of 2].
An area on the Stuart Shelf which is centred ~45 km north-northwest of Mount Gunson and 70 km south-east of Olympic Dam was taken up to explore primarily for possible economic buried Mesoproterozoic basement-hosted copper-gold deposits, perhaps of...-
Document
Published: 15 Nov 1913
-
Intercept Hill. Annual reports to licence expiry/full surrender, for the period 8/5/2003 to 14/7/2013. [Index Part 2 of 2].
In March 2010, once the terms of the joint venture agreement had been finalised, Argo passed its complete data sets to Xstrata, who immediately commenced a re-logging of Argo's drill cores besides conducting comprehensive unconstrained 3-D modelling...-
Document