Blanchewater Hill. Progress and final reports for the period 11/8/80 to 10/8/82.
Drilling of two percussion holes (aggregate 400 metres) near Yerila, south of Lake Blanche, failed to give encouragement to the search for possible Permian coal and Tertiary uranium in the southern Eromanga Basin / Lake Blanche Lineament uplift area...-
Document
-
Lake Cadibarrawirracanna. Progress and final reports to licence expiry/full surrender for the period 3/6/1980 to 2/12/1980.
Thirty-two shallow auger holes up to 2.76 m deep were drilled into the floor of Lake Cadibarrawirracanna, situated 70 km west of William Creek, in a search for possible potash-rich brines trapped by the lake sediments. The lacustrine sediments were...-
Document
-
Lake Phillipson area. Progress and technical reports for the periods 23/11/1978 to 22/11/1980, and 12/2/1981 to 11/5/1982. [forms Part 2 of a SADME - compiled Lake Phillipson coal deposit data package released in December 1994].
The licensee's 1981 coal search programme at Lake Phillipson had the following objectives: - delineation of the total extent of the coal measures; - resolution of seam stratigraphy and correlation of seams between the Main and West Areas; -...-
Document
-
Millers Creek Homestead. Progress reports and final report to licence expiry/full surrender, for the period 13/3/1980 to 28/3/1986.
Following a review of existing regional geophysical and geological data for the north-western Stuart Shelf, grid-based gravity and ground magnetic surveys were run to further outline two broad gravity highs associated with discrete magnetic anomalies,...-
Document
-
RB 90/00077 Skeleton 2. Well completion report.
Skeleton 2 penetrated sediments of the eastern Lake Eyre Basin, the Frome Embayment, and granitic basement of the Mount Painter Ridge. The hole records the southernmost known occurrence of Cadna-owie Formation in the Frome Embayment. Unexpectedly,...-
Document
Published: 01 Dec 1990
-
Haggard Hill, Whymlet Well, Bon Bon Outstation, McDouall Peak and Phar Lap Outstation (the Kingoonya Project). Joint annual reports and final report to licences' surrender, for the period 21/6/2006 to 9/4/2010.
Exploration of a 4600 square km project area comprising five licences in two contiguous groups within the Kingoonya region has targeted two distinct styles of uranium mineralisation. The primary focus was on possible sandstone - hosted deposits within...-
Document
Published: 16 Apr 1910
-
Mundowdna, Wilpoorinna and Dalarinna Hill (part of the Marree Project). Combined final report at licences' joint surrender, for the period 21/6/2006 to 20/3/2009.
Three areas located along the southern margin of the Eromanga Basin, east and south-east of Marree and adjacent to the Strzelecki Track, have been explored for possible economic sedimentary uranium accumulations in porous Mesozoic sandstones, as it...-
Document
-
Margaret Creek (part of the G2 Lineament Project). First and second partial relinquishments' combined report, for the period 13/10/2000 to 12/10/2004.
Diamond exploration undertaken within the relinquished portions of EL 2759, which are located immediately south of William Creek and near the Oodnadatta Track, was focussed on the margin of the Gawler Craton where it is cut by the NNW-trending G2...-
Document
-
PACE Theme 2 (drilling partnerships with PIRSA and industry): Year 3 partnership DPY3-15, Peake and Denison Inliers western flank Mesozoic sedimentary uranium mineral prospects. Project final report.
Approved PACE Initiative Year 3 drilling proposal DPY3-15 aimed to discover a roll-front style uranium deposit hosted in Mesozoic sandstones flanking the exposed radiogenic Peake and Denison Inliers, that is amenable to mining by in-situ leach...-
Document
Published: 13 Apr 1907
-
PACE Theme 2 (drilling partnerships with PIRSA and industry): Year 3 partnership DPY3-29, Mount Woods area sandstone-hosted uranium mineral prospects. Project final report.
As part of the PACE Initiative Year 3 collaborative drilling projects between PIRSA and the minerals industry, Goldstream carried out an approved programme of reverse circulation drilling on its Mount Woods area exploration tenements, into selected...-
Document
Published: 18 Dec 1906
-
Peake Creek. Annual reports and final report to licence expiry/full surrender, for the period 16/9/2005 to 15/9/2009.
An area located immediately west of the Denison Inlier of the Proterozoic Peake and Denison Ranges, approximately 70 km south-east of Oodnadatta, was explored for possible roll-front style sedimentary uranium deposits that may have formed within...-
Document
Published: 20 Oct 1909
-
Edward Creek. Annual reports and final report to licence expiry/full surrender, for the period 16/9/2005 to 15/9/2009.
An area located immediately west of the Denison Inlier of the Proterozoic Peake and Denison Ranges, approximately 90 km south-east of Oodnadatta, was explored for possible roll-front style sedimentary uranium deposits that may have formed within...-
Document
Published: 20 Oct 1909
-
ELs 4678 - 4689 (the Oodnadatta Project). Joint annual reports, plus final reports at licences' individual or joint full surrenders, for the period 22/2/2011 to 9/9/2014.
The Oodnadatta Project consisted originally of twelve exploration licenses covering 7125 square km in far northern South Australia, this mainly being ground situated to the south and south-east of Oodnadatta. Uranium Equities Limited (UEQ) believed...-
Document
Published: 28 Oct 1914
-
Data release - as updated [made at SA Director of Mines’ discretion] : Paralana Creek (part of the Beverley Project). Annual reports for the period 29/9/2009 to 15/11/2015.
Work undertaken on EL 4378 during the 2009-2010 reporting year included the drilling of 478 vertical rotary mud holes totalling 132,960 m, and core drilling totalling 4117 m performed in 16 of these holes for stratigraphic unit / resource...-
Document
Published: 24 Dec 1915
-
Abminga Diamond Project. Data release made at licence renewal [and project cessation]: progress reports and annual reports for the period 25/10/1993 to 17/3/2004.
The Abminga Diamond Project, undertaken by Caldera Resources NL, was granted exploration project status, including permission for EL joint reporting, in July 1996. This event followed up to two years of work by other operators on a number of...-
Document
-
PACE Theme 2 (drilling partnerships with PIRSA and industry): Year 1 partnership DPY1-47 - [prospecting for] water in Permian palaeochannels draining the Mount Woods Inlier. Project final report.
Development of the Prominent Hill copper-gold deposit in the Mount Woods region will require an adequate source of water to support planned mining and ore processing operations, currently estimated to involve at least 6 million tonnes of ore per year....-
Document
Published: 10 Jun 1905
-
[Results of in-house] Bench scale epsomite testwork.
Results of a programme of laboratory scale testwork conducted to investigate fresh water leaching of epsomite ore originating from Coober Pedy in South Australia are as follows: 1). The ore when leached readily producing brines of uniform...-
Document
Published: 16 Apr 1986
-
Lake Frome Project. Individual licence annual reports, joint annual reports and final reports to various constituent licences' joint full surrenders, for the period 16/4/2009 to 5/6/2015.
An area centred ~36 km west of Quinyambie Homestead has been explored for possible buried economic sedimentary uranium mineralisation of palaeochannel hosted roll-front style that may have formed in relatively more distal Tertiary basinal sediments,...-
Document
Published: 30 Mar 1915
-
Data release - as updated : Boundary Dam. Annual reports to licence expiry/full surrender, for the period 30/7/2007 to 29/7/2016.
A small area centred ~130 km north of Marla, and abutting the Northern Territory border along the northern side of Tieyon Station, has been explored for possible economic buried secondary uranium deposits, which Tianda Uranium (Tianda) thought could...-
Document
-
PACE Copper Discovery Drilling (drilling partnerships with DSD and industry): Year 9 partnership DPY9-10 - northern Curnamona Province, Woolatchi magnetic anomaly Proterozoic basement IOCG mineral prospect. Drilling project final report.
The PACE Initiative Year 9 collaborative drilling project DPY9-10, which was undertaken between the Callabonna joint venture partners and DSD, aimed to discover a new copper-gold mineralised Iron Oxide Copper-Gold (IOCG) magmatic centre, similar in...-
Document
Published: 30 May 1917