Carpie Puntha and Peterlumbo. Joint second partial surrender report, for the period 14/2/1989 to 13/2/1992. Plus: Carpie Puntha and Waddikee. Joint final report to licences' expiry/renewal, for the period 14/2/1989 to 24/6/1992.
TARGET: Possible commercial Menninnie Dam type stratabound or stratiform base metal deposits in the Cowell - Kimba - Buckleboo region. EXPLORATION: Field reconnaissance and rock chip geochemical sampling of prospective areas identified from...-
Document
-
Corunna. Progress and final reports for the period 22/7/91 to 21/7/92.
TARGET: Broken Hill or Aggeneys - Gamsberg type stratiform base metal deposits within the metamorphosed Palaeoproterozoic Hutchison Group chemical sediments in the Corunna area, possibly hosted by geochemically anomalous carbonate and silicate facies...-
Document
-
Waddikee. Progress and final reports to licence expiry for the period 25/6/91 to 24/6/92.
TARGET: Investigation of a previously untested magnetic anomaly located 25 km south-east of Kimba. EXPLORATION: Field reconnaissance and limited ironstone geochemical sampling. RESULTS: No significant metal assays were returned from outcropping...-
Document
-
Triple Hill. Progress reports to licence expiry/full surrender, for the period 10/7/1979 to 4/10/1982.
Exploration for possible buried occurrences of unconformity-related uranium mineralisation, undertaken within an area located approximately 26 km west-southwest of Cowell on eastern Eyre Peninsula, has included the acquistion during July 1979 of a 500...-
Document
-
Data release - as updated [made at SA Director of Mines' discretion] : Kolendo, Taringa, Nonning, Wipipippee and Menninnie Dam (the Menninnie Project). Joint annual reports for the period 1/1/2013 to 31/12/2016.
The Menninnie JV Project area consists of five contiguous exploration licences, and is considered prospective for Pb-Zn-Ag-Cu-Au-Mo-U deposits associated with past epithermal, porphyry, IOCG and skarn - forming geological environments. It lies in a...-
Document
-
Thurlga Ramp (part of the Eyre Peninsula Project, Corrobinnie Uranium JV and Thurlga JV periods). Data release : final report at licence expiry/full surrender, for the period 1/1/2013 to 3/5/2019.
During the report period, licensee Andromeda Metals did no on-ground exploration. During its agreed 3-year earn-in period, joint venturer Investigator Resources undertook the following work described herein: - acquisition of high resolution aerial...-
Document
Published: 19 Jul 1919
-
Tumby Bay. Progress and annual reports to licence surrender, for the period 16/1/1980 to 28/12/1982.
TARGET: Epithermal and unconformity - type uranium in Archaean to Early Proterozoic rocks of the southern Gawler Craton. EXPLORATION: - an aerial magnetic and radioactivity survey flown at 800 m, 1600 m and 400m spacing by Austirex in November 1979;...-
Document
Published: 21 Feb 1983
-
Cowell - Middleback Range and Sheoak Hill areas. Joint progress reports for the initial tenure period 15/3/1983 to 14/3/1984.
TARGET: Possible stratiform Pb-Zn-Ag mineralisation of the Broken Hill or Aggeneys-Gamsberg type associated with banded iron formations in Early Proterozoic metasediments. EXPLORATION: Regional ground magnetic surveys, geological mapping, 29 RAB...-
Document
-
Stony Hill (part of the Northern Eyre Peninsula JV Project). Final report at licence full surrender, for the period 2/12/2004 to 23/12/2016.
During the life of the subject licence, the focus of exploration was to determine the area's potential for DSO haematite iron ore, with a secondary consideration being magnetite and haematite BIF. After conducting geophysical surveys and exploratory...-
Document
Published: 17 Jan 1917
-
Data release - as updated [made at SA Director of Mines’ discretion] : Waddikee. Annual reports for the period 24/5/2010 to 31/1/2018.
During licence Year 6, on renewed EL 4662, Monax and its JV earn-in partner OMM undertook auger soil geochemical sampling, ground magnetic and IP surveys, and exploratory drilling in their continuing search for economic iron ore and manganese...-
Document
-
Data release - as updated [made at SA Director of Mines' discretion] : Verran and Malbrom (the Verran Project, then the Arno Graphite Project). Joint annual reports plus annual report, for the period 29/1/2014 to 28/1/2019.
Two licence areas together covering the hinterland to Arno Bay and Port Gibbon on eastern Eyre Peninsula, and extending as far north-westwards as Rudall, are being explored for economic buried graphite deposits that may have formed in deformed high...-
Document
-
Stony Hill. Combined annual/final report to licence full surrender, for the period 15/3/2016 to 14/3/2017.
No new work was carried out on the subject Stony Hill licence area during its past year. The South Australian Iron Ore Group Pty Ltd (SAIOG) has held this tenement (successively under ELs 3287/4451/5617) since 2/12/2004, but has now surrendered it in...-
Document
Published: 17 Jan 1917
-
Data release - as updated [made at SA Director of Mines’ discretion] : Middleback Range and Moonabie Hills. Joint annual reports for the period 1/2/2007 to 30/1/2019, plus surrender reports to 9/7/2023.
Project Connelly is designed to target haematite mineralisation on OneSteel's mining and exploration leases, including EL 3516 Middleback Range, with the aim of adding to the haematite reserve. In addition to the exploration programme, reserve...-
Document
Published: 29 Mar 1918
-
PACE Discovery Drilling (drilling partnerships with DSD and industry): Year 8 partnership DPY8-31 - Peterlumbo Hill area, Eyre Peninsula, skarn and/or porphyry type Mesoproterozoic epithermal Cu-Au and Ag-base metal prospects. Drilling final report.
Investigator Resources (IVR) applied on 30/1/2015 to participate in the PACE Initiative Year 8 (2015) collaborative drilling grant program between industry and government being administered by DSD. The application for subsidy funds submitted by IVR...-
Document
Published: 20 Jan 1916
-
Data release - as updated [made at SA Director of Mines discretion]: the Eyre Peninsula Project. Joint annual reports for the period 29/12/2013 to 28/12/2018.
During the 2014 project reporting year, licensee Adelaide Resources undertook a research and development phase surface-based biogeochemical and field portable X ray fluorescence (FPXRF) spectrometric sampling programme over its Baggy Green gold...-
Document
Published: 22 Apr 1919
-
Final Report - Unravelling the Stratigraphy of the Middleback Ranges ADI RD03-385 [Accelerated Discovery Initiative Round 3, 2023].
In 2022 SIMEC Mining/Onesteel Manufacturing Pty Ltd successfully applied for up to $270,000 of funding through the South Australian Government’s Accelerated Discovery Initiative (ADI) program. The company proposed to undertake RC and diamond drilling...-
Document
-
Eureka Bluff, Mount Nott and Mount Ive (the Gawler Range Volcanics Project). Joint venture partners' progress reports and final reports, for the period 17/6/1983 to 16/6/1988.
TARGET: Diamonds in possible kimberlite intrusives; and (as JV objectives), possible exhalative lead-zinc-silver deposits of Broken Hill or Aggeneys - Gamsberg type, emplaced within the Early Proterozoic Hutchison Group, plus possible epithermal...-
Document
Published: 10 Oct 1988
-
Mount Olinthus. Progress reports plus interim final report to licence expiry/renewal, for the period 12/7/1978 to 7/11/1987.
TARGET: Unconformity related, vein-like and vein-type uranium in the Cleve Metamorphics, Katunga Dolomite and Mangalo Schist; lead-zinc sulphides of Broken Hill or Balmat-Edwards type in the Hutchison Group. EXPLORATION: Uranium exploration...-
Document
-
PACE Copper Discovery Drilling (drilling partnerships with DSD and industry): Year 9 partnership DPY9-11, Thurlga Ramp, northern edge of Cleve Domain, volcanic epithermal / hydrothermal replacement type precious metal prospects. Drilling final report.
A licence area, which lies adjacent on the west to Investigator Resources' Peterlumbo Hill EL 5368 containing the Paris silver deposit (where there is a currently inferred resource of 42 Moz @ 139 ppm Ag), is being explored under a joint venture with...-
Document
-
The Northern Eyre Peninsula JV Project. Data release made in lieu of submitting a licence final report at the full surrender of EL 5170 Kimba Gap: Joint annual reports for the period 1/2/2013 to 9/2/2017.
During the Northern Eyre Peninsula Project (NEPP) 2013-2014 reporting year, exploration field work took place on two of the six project tenements. On EL 4884 Minbrie, a single 151 m deep vertical RC drillhole, BURC092, was completed in August 2013,...-
Document
Published: 25 Sep 1918